Question: Fill in the table below with the three point estimate (E) and variance (V) for each task. Task Predecessors a m b E V A
Fill in the table below with the three point estimate (E) and variance (V) for each task.
| Task | Predecessors | a | m | b | E | V |
| A | none | 3 | 5 | 8 | ||
| B | A | 2 | 3 | 9 | ||
| C | A | 3 | 4 | 7 | ||
| D | B | 2 | 5 | 7 | ||
| E | B and C | 2 | 4 | 9 | ||
| F | D and E | 1 | 5 | 8 |
What is the critical path?
1. ABCD
2. ABDF
3. ABEF
4. ABCF
5. ACDF
4. ACEF
| What is the duration of the project? | Answer |
| What is the variance of the duration of the project? | Answer |
| Find the Probability Duration <17 | |
| Z Value | Answer |
| Probability | Answer |
| Find the Probability Duration >19 | |
| Probability Duration <19 | |
| Probability Duration >19 |
What is the probability that 18| Answer | |