Question: Fill in the table below with the three point estimate (E) and variance (V) for each task. Task Predecessors a m b E V A

Fill in the table below with the three point estimate (E) and variance (V) for each task.

Task Predecessors a m b E V
A none 3 5 8
B A 2 3 9
C A 3 4 7
D B 2 5 7
E B and C 2 4 9
F D and E 1 5 8

What is the critical path?

1. ABCD

2. ABDF

3. ABEF

4. ABCF

5. ACDF

4. ACEF

What is the duration of the project? Answer
What is the variance of the duration of the project? Answer

Find the Probability Duration <17
Z Value Answer
Probability Answer

Find the Probability Duration >19
Probability Duration <19
Probability Duration >19

What is the probability that 18 Answer

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!