Question: Find out the network and identify critical path, activity slack. Activity Activity time (days) Immediate predecessor A 3 B 4 A 5 D 12 A,

Find out the network and identify critical path, activity slack. Activity Activity time (days) Immediate predecessor A 3 B 4 A 5 D 12 A, B E 5 F 2 B, E G 4 C D H 6 D I 4 F G J 7 E, H K 3
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
