Question: 4. Find out the network and identify critical path, activity slack. Activity Activity time (days) Immediate predecessor A 3 B 4. A 5 D 12

4. Find out the network and identify critical path, activity slack. Activity Activity time (days) Immediate predecessor A 3 B 4. A 5 D 12 A, B E 5 F 2 B, E G 4 H 6 D I 4 F, G J 7 E, H K 3 I C, D