Question: Find the time to complete the project, whose activities are shown below. ACT. S J | W H HYN Z DURATION 3 2 4 6
Find the time to complete the project, whose activities are shown below.

ACT. S J | W H HYN Z DURATION 3 2 4 6 1 2 3 FOLLOWED BY H Y W H S Z H **** RELATIONSHIP S.S=2 F-S=1 F-F=5 S-S=3 F-S=1 F-S=3 S-S=2 F-S=2 F-S=2 S-F=4 ****
Step by Step Solution
3.41 Rating (157 Votes )
There are 3 Steps involved in it
Answer According to give... View full answer