Question: Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 8 12 B 4 9 C 3 6 D 7 7 E 5 20 Using the earliest due date (EDD) rule, it can be concluded that the average tardiness for these five jobs is _____.
Question 3 options:
a. 3 days.
b. 5 days.
c. 6 days.
d. 4 days.
Step by Step Solution
There are 3 Steps involved in it