Question: Following is a partially completed Work Breakdown Structure for a house construction project. House 1 . 1 Foundation 1 . 3 Roof 1 . 1
Following is a partially completed Work Breakdown Structure for a house construction project.
House
Foundation
Roof
Concrete
Paint
Roof Truss
Which of the following statements is the most correct regarding this project's WBS:
A Work Package named Plaster" would be placed under SubDeliverable Foundation"
A Work Package named Plaster" would be placed under Top Deliverable WallsCeilings
A Work Package named Plaster" would be placed under Work Package WallsCeilings
A Work Package named Plaster" would be placed under SubDeliverable WallsCeilings