Question: For a process shown with 4 operations, what is the ideal output that can be expected in a shift as shown below? Operation A Operation

For a process shown with 4 operations, what is the ideal output that can be expected in a shift as shown below? Operation A Operation B Operation C Operation D C/T mins 16 18 24 32 Shift time mins 240 Group of answer choices 10.7 units 11.0 units 8.4 units 13.3 units