Question: For a process shown with 4 operations, what is the ideal output that can be expected in a shift as shown below? Operation Operation Operation
For a process shown with 4 operations, what is the ideal output that can be expected in a shift as shown below? Operation Operation Operation Operation A B C D C/T mins 25 27 33 41 Shift time mins 420 10.7 units 11.0 units O 8.4 units 13.3 units
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts