Question: For a project activity the optimistic, most likely, and pessimistic times are 2 2 , 2 5 , and 3 4 . What time should

For a project activity the optimistic, most likely, and pessimistic times are 22,25, and 34. What time should be used when conducting a critical path analysis?
Group of answer choices
25
26
22
27