Question: For activities not on the critical path for which the earliest and latest start times are not equal, Select one: O a. slack time exists

For activities not on the critical path for which

For activities not on the critical path for which the earliest and latest start times are not equal, Select one: O a. slack time exists b. the project has crashed c. critical path time exists d. beta distribution exists