Question: If the Optimistic duration is 5 days, the Most Likely duration is 10 days, and the Pessimistic duration is 20 days, what is the PERT
If the Optimistic duration is 5 days, the Most Likely duration is 10 days, and the Pessimistic duration is 20 days, what is the PERT estimated duration for the task? Round to the nearest whole number.
A. 20 days
B. 15 days
C. 5 days
D. 13 days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
