Question: For each task not on the critical path, by how much could the start be delayed assuming that each task on critical path starts at

For each task not on the critical path, by how

For each task not on the critical path, by how much could the start be delayed assuming that each task on critical path starts at the earliest opportunity?

\begin{tabular}{|l|l|l|} \hline Task number & Duration in week & Depends on task \\ \hline 1 & 6 & \\ \hline 2 & 3 & \\ \hline 3 & 4 & 1 \\ \hline 4 & 6 & \\ \hline 5 & 5 & 1,3 \\ \hline 6 & 3 & 1,3,4 \\ \hline 7 & 2 & 5 \\ \hline 8 & 5 & 6 \\ \hline 9 & 3 & 2,8 \\ \hline 10 & 7 & 7,8 \\ \hline \end{tabular}