Question: For output to equal forecasted demand, what should be the actual Takt time for this production? For output to equal demand, what is the minimum
For output to equal forecasted demand, what should be the actual Takt time for this production?
For output to equal demand, what is the minimum number of workstations needed?
Assign the task to the workstations. How many workstations did it actually take?
What will be the effiency of the production line that uses the actual number of workstations?
A manufacturer needs to produce 450 lithium battery packs per 16 hour day. The discrete tasks required to produce the battery have been identfied, timed in seconds, and ordered as indicated in the table below. The precedence diagram is drawn below