Question: Questions: For output to equal forecasted demand, what should be the actual Takt time for this production? For output to equal forecasted demand, what is
Questions:
For output to equal forecasted demand, what should be the actual Takt time for this production?
For output to equal forecasted demand, what is the minimum number of workstations needed?
Assign the task to the workstations.. How many workstations did it actually take?
What will be the efficiency of the production line that uses the actual number of workstations?
_____________Please draw the letters and where they connect!:)
A manufacturer needs to produce 300 coffee pots per 8 hour day. The discrete tasks required to produce a coffee pot have been identified, timed in seconds, and ordered as indicated in the table below. The precedence diagram is drawn below.
| Task | Time | Predecessors |
| A | 80 | -- |
| B | 25 | A |
| C | 35 | A |
| D | 20 | B, C |
| E | 50 | C |
| F | 70 | E |
| G | 45 | D |
| H | 25 | G |
| I | 15 | G |
| J | 43 | F, H, I |
Step by Step Solution
There are 3 Steps involved in it