Question: For the activities shown in the table below, please draw the network diagram. Activity A B C D E Duration (days) 10 8 2 4
For the activities shown in the table below, please draw the network diagram.
Activity
A
B
C
D
E
Duration (days)
10
8
2
4
5
Immediate Predecessors
---
---
A
A
B,C,D