Question: For the below activities in the table, after drawing the PDM, what is the TF for activity D ? Activity ID Duration (Days) Predecessors (IPA)
For the below activities in the table, after drawing the PDM, what is the TF for activity D?
| Activity ID | Duration (Days) | Predecessors (IPA) |
| A | 1 | --- |
| B | 3 | A |
| C | 4 | A |
| D | 2 | B |
| E | 3 | C |
| F | 5 | D, E |
| G | 1 | F |
| H | 2 | G |
| I | 3 | G, H |
Select one:
a. None
b. 1
c. 2
d. 0
e. 6
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
