Question: For the below activities in the table, after drawing the PDM, what is the FF for activity H ? Activity ID Duration (Days) Predecessors (IPA)

For the below activities in the table, after drawing the PDM, what is the FF for activity H?

Activity ID

Duration (Days)

Predecessors (IPA)

A

1

---

B

3

A

C

4

A

D

2

B

E

3

C

F

5

D, E

G

1

F

H

2

G

I

3

G, H

Select one:

a. 2

b. 0

c. 1

d. 6

e. None