Question: for the current problem, should the earned value be $17500 * 2 based on the nuber of rooms completed? you are constructing 6 sdditiionalrooms on
for the current problem, should the earned value be $17500 * 2 based on the nuber of rooms completed?
you are constructing 6 sdditiionalrooms on an office building. each of the sixrooms is identical and the prone tex cost for the project is $100,000 and is expected to take5 weeks.
at the end of the 2nd week. you have spent $17,500 per room and have finished 2 rooms and have finished 2 rooms , you are readyto begin on the 3rd. what os the actual cost?