Question: For the following table and report make earned value analysis to this project and represent the project situation (15 marks). Activity Predecessor duration Cost/day Total

For the following table and report make earned

For the following table and report make earned value analysis to this project and represent the project situation (15 marks). Activity Predecessor duration Cost/day Total cost Actual Actual cost compete % A None 2 200 400 100% 400 B A 3 300 900 100% 1100 B 3 300 900 33% 500 D B 2 100 200 50% 100 E D 3 50 150 0% 0