Question: For the following table and report make earned value analysis to this project and represent the project situation (15 marks), Activity Predecessor duration A Cost/day

For the following table and report make earned

For the following table and report make earned value analysis to this project and represent the project situation (15 marks), Activity Predecessor duration A Cost/day None Total cost B 2 Actual compete% A 200 Actual cost 3 400 B 300 100% D 3 900 400 B 300 100% E 2 900 1100 D 100 33% 3 200 500 50 50% 150 100 0% O 0 FID

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!