Question: For the given data, crash the project completely. ACTIVITY PREDECESSOR NORMAL TIME(DAYS) MAX CRASH TIME NORMAL COST$ CRASH SLOPE A NONE 3 0 60 0

For the given data, crash the project completely.

ACTIVITY

PREDECESSOR

NORMAL TIME(DAYS)

MAX CRASH TIME

NORMAL COST$

CRASH SLOPE

A

NONE

3

0

60

0

B

NONE

7

1

30

50

C

A

5

3

50

13.33

D

A

6

1

30

20

E

C,B

4

2

40

30

1.What is the normal project duration? = BLANK-1

2. Whatis the normal project cost? = BLANK-2

3. What is the project cost when fully crashed? = BLANK-3

4. Which activities were crashed to reach the final crashed duration? List in order = BLANK-4

5. What is the project duration when completely crashed? = BLANK-5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!