Question: For the given data, crash the project completely. ACTIVITY PREDECESSOR NORMAL TIME(DAYS) MAX CRASH TIME NORMAL COST$ CRASH SLOPE A NONE 3 0 60 0
For the given data, crash the project completely.
| ACTIVITY | PREDECESSOR | NORMAL TIME(DAYS) | MAX CRASH TIME | NORMAL COST$ | CRASH SLOPE |
| A | NONE | 3 | 0 | 60 | 0 |
| B | NONE | 7 | 1 | 30 | 50 |
| C | A | 5 | 3 | 50 | 13.33 |
| D | A | 6 | 1 | 30 | 20 |
| E | C,B | 4 | 2 | 40 | 30 |
1.What is the normal project duration? = BLANK-1
2. Whatis the normal project cost? = BLANK-2
3. What is the project cost when fully crashed? = BLANK-3
4. Which activities were crashed to reach the final crashed duration? List in order = BLANK-4
5. What is the project duration when completely crashed? = BLANK-5