Question: For the given data, crash the project completely. Activity---- Predecessor---------Normal Time (Days)----- Max Crash Time------Normal Cost $------ Crash Slope ---- A---------------none------------------3-----------------------------------0--------------------------------60-----------------------0 ---- B---------------none------------------7-----------------------------------1--------------------------------30-----------------------50 ---- C---------------

For the given data, crash the project completely.

Activity---- Predecessor---------Normal Time (Days)----- Max Crash Time------Normal Cost $------ Crash Slope

---- A---------------none------------------3-----------------------------------0--------------------------------60-----------------------0

---- B---------------none------------------7-----------------------------------1--------------------------------30-----------------------50

---- C--------------- A----------------------5-----------------------------------3--------------------------------50-----------------------13.33

---- D--------------- A----------------------6-----------------------------------1--------------------------------30-----------------------20

---- E--------------- C,B--------------------4-----------------------------------2--------------------------------40-----------------------30

1.What is the normal project duration? = BLANK-1

2. What is the normal project cost? = BLANK-2

3. What is the project cost when fully crashed? = BLANK-3

4. Which activities were crashed to reach the final crashed duration? List in order = BLANK-4

5. What is the project duration when completely crashed? = BLANK-5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!