Question: For the given data, crash the project completely. Activity---- Predecessor---------Normal Time (Days)----- Max Crash Time------Normal Cost $------ Crash Slope ---- A---------------none------------------3-----------------------------------0--------------------------------60-----------------------0 ---- B---------------none------------------7-----------------------------------1--------------------------------30-----------------------50 ---- C---------------
For the given data, crash the project completely.
Activity---- Predecessor---------Normal Time (Days)----- Max Crash Time------Normal Cost $------ Crash Slope
---- A---------------none------------------3-----------------------------------0--------------------------------60-----------------------0
---- B---------------none------------------7-----------------------------------1--------------------------------30-----------------------50
---- C--------------- A----------------------5-----------------------------------3--------------------------------50-----------------------13.33
---- D--------------- A----------------------6-----------------------------------1--------------------------------30-----------------------20
---- E--------------- C,B--------------------4-----------------------------------2--------------------------------40-----------------------30
1.What is the normal project duration? = BLANK-1
2. What is the normal project cost? = BLANK-2
3. What is the project cost when fully crashed? = BLANK-3
4. Which activities were crashed to reach the final crashed duration? List in order = BLANK-4
5. What is the project duration when completely crashed? = BLANK-5