Question: For the given problem, Task Predecessor Normal Time ( days ) Crash Time ( days ) Normal Cost Crash Cost A 3 2 4 0
For the given problem,
Task
Predecessor
Normal Time
days
Crash Time
days
Normal Cost
Crash Cost
A
B
C
A B
D
A
E
C
F
D E
Answer the following questions:
a What is the normal cost of the project? Select $$$$$
b What is the length of the project? Select days", days", days", days", days"
c Which activity would you crash first to reduce the project by one day and what will be the cost to crash? Select A; $F; $B; $E; $C; $
d What is the maximum amount of days that this project can be crashed by Select days", days", days", days", days" and what is the total cost? Select $$$$$
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
