Question: For the given problem, Task Predecessor Normal Time ( days ) Crash Time ( days ) Normal Cost Crash Cost A 3 2 4 0

For the given problem,
Task
Predecessor
Normal Time
(days)
Crash Time
(days)
Normal Cost
Crash Cost
A
3
2
40
120
B
7
5
30
80
C
A, B
5
4
45
90
D
A
6
5
30
50
E
C
4
2
40
100
F
D, E
5
4
55
75
Answer the following questions:
a. What is the normal cost of the project?[ Select ]["$440","$515","$320","$240","$190"]
b. What is the length of the project?[ Select ]["21 days", "26 days", "23 days", "16 days", "17 days"]
c. Which activity would you crash first to reduce the project by one day and what will be the cost to crash?[ Select ]["A; $80","F; $20","B; $25","E; $60","C; $13.33"]
d. What is the maximum amount of days that this project can be crashed by?[ Select ]["9 days", "7 days", "15 days", "13 days", "6 days"], and what is the total cost?[ Select ]["$175","$0.00","$150","$145","$125"]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!