Question: For the given problem, Task Predecessor Normal Crash Normal Crash Time Time Cost Cost A 3 2 40 120 B 7 5 30 80 C

For the given problem, Task Predecessor Normal
For the given problem, Task Predecessor Normal Crash Normal Crash Time Time Cost Cost A 3 2 40 120 B 7 5 30 80 C AB 5 4 45 90 D A 6 ch 5 30 50 E B, C 4. N 40 100 F F D, E 5 4 55 75 Answer the following questions: a. What is the normal cost of the project? [Select ] b. Which activity would you crash first to reduce the project by one day and what will be the cost to crash? (Select ] c. Which activity would you crash next by an additional day and what would be the total 2 day cost of crashing? (Select]