Question: For the given problem, Task Predecessor Normal Time ( days ) Crash Time ( days ) Normal Cost Crash Cost A 3 2 4 0

For the given problem,
Task
Predecessor
Normal Time
(days)
Crash Time
(days)
Normal Cost
Crash Cost
A
3
2
40
120
B
7
5
30
80
C
A, B
5
4
45
90
D
A
6
5
30
50
E
C
4
2
40
100
F
D, E
5
4
55
75
Answer the following questions:
a. What is the normal cost of the project?
[ Select ]
b. What is the length of the project?
[ Select ]
c. Which activity would you crash first to reduce the project by one day and what will be the cost to crash?
[ Select ]
d. What is the maximum amount of days that this project can be crashed by?
[ Select ]
, and what is the total cost?
[ Select ]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!