Question: For the given problem, Task Predecessor Normal Time ( days ) Crash Time ( days ) Normal Cost Crash Cost A 3 2 4 0

For the given problem,
Task
Predecessor
Normal Time
(days)
Crash Time
(days)
Normal Cost
Crash Cost
A
3
2
40
120
B
7
5
30
80
C
A, B
5
4
45
90
D
A
6
5
30
50
E
C
4
2
40
100
F
D, E
5
4
55
75
Answer the following questions:
a. What is the normal cost of the project?
$240
b. What is the length of the project?
21 days
c. Which activity would you crash first to reduce the project by one day and what will be the cost to crash?
F; $20
d. What is the maximum amount of days that this project can be crashed by?
, and what is the total cost?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!