Question: For the network below, calculate for each task, BCWP, BCWS, ACWP, CV, SV, CPI, SPI. Calculate these numbers for the entire project as well. Comments
For the network below, calculate for each task, BCWP, BCWS, ACWP, CV, SV, CPI, SPI.
Calculate these numbers for the entire project as well. Comments on the status of your project:

B/9 E/5 A/10 - . G14 F/9 D/6 For each of the seven tasks that make up the project above, assume the following: Actual Percent TASK Expenditure Expenditure Duration Complete s/Day s to Date 100% $1,000 $13,000 100% $1,200 $9,000 30% $1,000 $4,000 20% $1,5001 $5,000 40% $1,500 $3,000 0% $1,000 10% $1,200 $0 Fill out the table below: TOTAL ACWP BCWS BCWP TASK %COMP | BUDGET (PV) (EV) $10,000 100% $13,000 100% $9,000 30% $4,000 20% $5,000 40% $3,000 0% $0 Totals $34,000 cv sv C PI SPI (AC) 0% Project is 14 days old -- 14 business days have transpired Calculate the following: BAC = EAC = Problem 12-18 12-15 for classes Problem 12-15 12-18 for classes EX 12-A Homework EX 12-B Homework +