Question: For the network information given below, - Construct an AoN diagram [ 7 points ] - Compute and tabulate the four activity dates ( ESD

For the network information given below,
- Construct an AoN diagram [7 points]
- Compute and tabulate the four activity dates (ESD, EFD, LSD, and LFD) and the total and free floats for each activity. Start calculation from zero [8 points]
- In the network, Identify critical activities, and critical path(s)[5 points]
- Draw bar chart and generate project recourses profile (resources aggregation)[5 points]
-This is a combination SS+FF relationship with no lags.
 For the network information given below, - Construct an AoN diagram