Question: For the project information given below, ( i ) Draw a project network diagram; ( ii ) compute ES , EF , LS , LF
For the project information given below, i Draw a project network diagram; ii compute ES EF LS LF times, and Slack times; iii Indicate O Critical path in RED colour.
Note: Draw the network diagram on a piece of paper and manually compute the above.
tableIDDescription,,PredecessorAOrder review,,NoneBOrder standard parts,,ACProduce standard parts,,DDesign custom parts,,AESoftware development,AFManufacture custom hardware,AGAssemble,CDHTest,B F