Question: Form 1 A 1 0 thick 5 high concrete wall is being formed using ( 1 ) / ( 2 ) plyform, No 2 DF

Form 1
A 10 thick 5 high concrete wall is being formed using (1)/(2) plyform, No 2 DF-L 2x4 studs
and Single No.2 DF-L 2x4 wale. Ties have an 1,850 lb capacity and the plywood face runs
perpendicular to the studs. Concrete will be delivered at 70,3 slump and will be internally
vibrated. Placement rate at 6 ft/hr. Design the formwork for the wall where appearance is
architecturally important.
\Gamma c =145 pcf
Type I-II cement
Use APA Plyform B-B Class 1 Exterior 1/2x 48 x 96
Concrete Wall Placement
Find the placement rate for a wall where the wall is 5ft tall, 1,800 ft long and 10 inches thick. The
concrete front loading trucks will bring a total of 4 cy per truck with two trucks delivering placing
concrete simultaneously at the same rate of 12 minutes per truck.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!