Question: From the following data set, create a Gantt Chart and a PERT Chart. For the Gantt chart, DO NOT assume a start date -- just
From the following data set, create a Gantt Chart and a PERT Chart. For the Gantt chart, DO NOT assume a start date -- just label the weeks 1, 2, 3 etc. For the PERT chart show the length of each possible path and identify the critical path. Weeks Must Follow A Collect Requirements 2 -- B Analyze Processes 3 A C Analyze Data 3 B D Design Processes 5 B E Design Data 6 B F Design Screens 1 C, D G Design Reports 4 D, E H Program 5 F, G I Train 2 G J Install 2 H, I
Step by Step Solution
There are 3 Steps involved in it
Activity Description A B Week Must Follow Collect Re... View full answer