Question: project management From the following information, develop an AON project network Complete the forward and backward pass, compute activity slack, and identify the critical path.

project management
project management From the following
From the following information, develop an AON project network Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take? ID A B Predecessor None Description Survey site Excavate site Install power lines Install drainage Pour foundation Time 4 4 4 1 D E B C D days The project will take The critical path is The late start on Activity Cis The slack on Activity C is The slack on Activity Dis The early start on Activity E is days days days days 76 of 81 Next > ** o grevious a to search 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!