Question: From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. What is
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path.
What is the critical path? (describe the path as activity with task ID, eg. A, B, C, D, E)
How many days will the project take?
ID Time A B C D D E Description Survey site Install drainage Install power lines Excavate site Pour foundation Predecessor None A A A B, C D 2 5 3 4 3Step by Step Solution