Question: From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?
| ID | Description | Predecessor | Time |
| A | Survey site | None | 4 |
| B | Excavate site | A | 6 |
| C | Install power lines | B | 4 |
| D | Install drainage | B | 1 |
| E | Pour foundation | C, D | 2 |
a.The project will take _____days.
b. The critical path is _____
c. The late start on Activity C is ______ days.
d. The slack on Activity C is _____ days.
e.The slack on Activity D is _____ days.
f.The early start on Activity E is ______days.