Question: Problem 1 (30 points) The following table presents project information (time unit in months) Activit y Predecessors Pessimisti c Duration Most likely Duration Optimisti c

Problem 1 (30 points) The following table presents project information (time unit in months)

Activit y Predecessors Pessimisti c Duration Most likely Duration Optimisti c Duration A ____ 12 10 7 B ____ 8 5 4 C A 9 7 5 D B 7 5 4 E B, D 12 10 8 F B, D 7 4 3 G E, F 10 8 5

a) Draw an AON network diagram for the project. (5 pts)

b) Determine the critical path of the project. (5 pts)

c) Calculate the expected time for all activities. (5 pts)

d) What is the expected project completion duration? (5 pts)

e) Calculate the variance of the critical path. (5 pts)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!