Question: From the project plan, we that a project has a total budgeted cost of $970,262 and a project completion time of 17 weeks. At the

From the project plan, we that a project has a
From the project plan, we that a project has a total budgeted cost of $970,262 and a project completion time of 17 weeks. At the moment, the project has been in a Time Rr performing stage. At the end of week 7 , the project progress report stiows that the project has consumed a total of $367,243, the project cost performance index is 1.22. and the schedile pertormance index is 0.91. What is the value of the cost variance at the end of week 7