Question: From the project plan, we that a project has a total budgeted cost of $977,251 and a project completion time of 17 weeks. At the
From the project plan, we that a project has a total budgeted cost of $977,251 and a project completion time of 17 weeks. At the moment, the project has been in a performing stage. At the end of week 8, the project progress report shows that the project has consumed a total of $327,688, the project cumulative earned value is $355,895, and the project schedule performance index is 0.89.
What is the estimated project cost at completion if the project continues at the cost performance index of 1.0?
Use at least 4 decimals.