Question: From the project plan, we that a project has a total budgeted cost of $926,701 and a project completion time of 17 weeks. At the

From the project plan, we that a project has a
From the project plan, we that a project has a total budgeted cost of $926,701 and a project completion time of 17 weeks. At the moment, the project has been in a performing stage. At the end of week 8, the project progress report shows that the project has consumed a total of $323,218, the project cumulative earned value is $356,503, and the project schedule performance index is 0.80. What is the estimated project cost at completion if the project continues at the cost performance index of 1.0 ? Use at least 4 decimals

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!