Question: From this PERT / CPM network, answer the following questions. the arrows by weeks. [ 1 . 5 Mark each ] Q 7 . If

From this PERT/CPM network, answer the following questions.
the arrows by weeks. [1.5 Mark each]
Q7. If variance for this project 6, what prob. To finish project between 23 and 33 weeks
a.0.976
b.0.477
c.0.998
d.0.498
e. none of them