Question: Using the following information, draw the CPM chart and answer the following questions: Activity Predecessor Time (Weeks) A - 3 B A 6 C A
Using the following information, draw the CPM chart and answer the following questions:
| Activity | Predecessor | Time (Weeks) |
| A | - | 3 |
| B | A | 6 |
| C | A | 11 |
| D | B | 2 |
| E | C | 3 |
| F | D, E | 4 |
| G | F | 5 |
- How may weeks will the project take to complete?
- What is the Critical Path?
- If there is slack (or float) how many weeks and at which activity node?
Define the following terms:
- CPM
- Critical Path
- Crash
- PERT
- Slack