Question: Using the following information, draw the CPM chart and answer the following questions: Activity Predecessor Time (Weeks) A - 3 B A 6 C A

Using the following information, draw the CPM chart and answer the following questions:

Activity

Predecessor

Time (Weeks)

A

-

3

B

A

6

C

A

11

D

B

2

E

C

3

F

D, E

4

G

F

5

  1. How may weeks will the project take to complete?
  2. What is the Critical Path?
  3. If there is slack (or float) how many weeks and at which activity node?

Define the following terms:

  1. CPM
  2. Critical Path
  3. Crash
  4. PERT
  5. Slack