Question: Using the following information, draw the CPM chart and answer the following questions: Activity Predecessor Time ( Weeks ) A - 3 B A 6
Using the following information, draw the CPM chart and answer the following questions:
Activity Predecessor Time Weeks
A
B A
C A
D B
E C
F D E
G F
How many weeks will the project take to complete?
What is the Critical Path?
If there is slack or float how many weeks and at which activity node?
Define the following terms:
CPM
Critical Path
Crash
PERT
Slack