Question: Function points in the project: 252 Software engineers assigned to this team: 5 Function point productivity per software engineer: 5 per month Workdays per typical

Function points in the project: 252

Software engineers assigned to this team: 5

Function point productivity per software engineer: 5 per month

Workdays per typical month: 22

Productivity hours per typical workday: 8

Gross Hourly wage rate per software engineer (does not include fringe benefits): 50

Overhead (fringe benefit, other direct overhead) rate: 40%

G&A rate: 11.5

Proposed profit: 10%

What is the total cost to the customer for the project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!