Question: Function points in the project: 252 Software engineers assigned to this team: 5 Function point productivity per software engineer: 5 per month Workdays per typical
Function points in the project: 252 Software engineers assigned to this team: 5 Function point productivity per software engineer: 5 per month Workdays per typical month: 22 Productivity hours per typical workday: 8 Gross Hourly wage rate per software engineer (does not include fringe benefits): 50 Overhead (fringe benefit, other direct overhead) rate: 35% G&A rate: 11.5 Proposed profit: 10% What is the total cost to the customer for the project