Question: Function points in the project: 252 Software engineers assigned to this team: 5 Function point productivity per software engineer: 5 per month Workdays per typical
Function points in the project: 252
Software engineers assigned to this team: 5
Function point productivity per software engineer: 5 per month
Workdays per typical month: 22
Productivity hours per typical workday: 8
Gross Hourly wage rate per software engineer (does not include fringe benefits): 50
Overhead (fringe benefit, other direct overhead) rate: 35%
G&A rate: 11.5
Proposed profit: 10%
What is the total cost to the customer for the project?
676,086.05
734,369.33
509,978.70
458,980.83
701,126.27