Question: F A project's critical path is CDFGI. The expected time and the standard deviation of each activity are as follows. Activity ABC D E F

F A project's critical path is CDFGI. The

F A project's critical path is CDFGI. The expected time and the standard deviation of each activity are as follows. Activity ABC D E F G H Expected 12 15 14 9 10 1 15 Time Standard Deviation 110 4 17 16 14 10 13 12 5 2 18 16 What is the project standard deviation? keep two decimals if not exact, either round up or down is ok. For example, for 0.1346, (0.13 or.13) and (0.14 or.14) are correct