Question: Question 4 20 pts A project's critical path is CDFGI. The expected time and the standard deviation of each activity are as follows. IC D

Question 4 20 pts A project's critical path is

Question 4 20 pts A project's critical path is CDFGI. The expected time and the standard deviation of each activity are as follows. IC D E F G H 18 Activity B Expected 12 15 Time Standard 110 4 Deviation 16 14 19 10 11 15 [10 14 10 12 17 5 16 What is the project standard deviation? keep two decimals if not exact, either round up or down is ok. For example, for 0.1346, (0.13 or. 13) and (0.14 or 14) are correct