Give 2 common reasons why scope creep occurs? Give 2 examples of what project managers can do
Fantastic news! We've Found the answer you've been seeking!
Question:
Give 2 common reasons why scope creep occurs?
Give 2 examples of what project managers can do to control Scope Creep.
Reporting performance keeps stakeholders informed about how resources are being used to achieve project objectives.
Describe the three types of project reporting that a project manager would commonly use to inform the stakeholders of project progress.
You have a project where Cost Performance Indicator (CPI) of .80 which means we are spending more money than we should spend. And we have Schedule Performance Indicator (SPI) of 1.20, which means we are ahead of schedule. Do you think we should be worried because we are spending more than budgeted money? Explain your answer