Question: Given a simple project illustrated in the following table Jimmediate Time Activity Predecessors (weeks) 1 2 2 1 2 12 2 4 12 5 3,4

Given a simple project illustrated in the
Given a simple project illustrated in the following table Jimmediate Time Activity Predecessors (weeks) 1 2 2 1 2 12 2 4 12 5 3,4 3 |||| Assume that "Activity 1" actually finished at 3 weeks, and "Activity 2" actually finished at 5 weeks. Given the actual project progress, what is the expected project completion time? 12 13 O 10 O 11