Question: Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 - 2 2 1 3 3 1 4 4 2
Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 - 2 2 1 3 3 1 4 4 2 2 5 3, 4 2 Assume that "Activity 1" actually finished at 3 weeks, "Activity 2" actually finished at 7 weeks, and "Activity 3" actually finished at 6 weeks. Given the actual project progress, what is the ES (earliest start time) of "Activity 5